Seattle NHL expansion team arena on schedule to open in summer 2021

Features:

The old arena grandstands have been removed, and with the windows gone the public has a clear look through the structure. All that remains under the roof are mounds of dirt along the outside of the building. In the center of the floor, a giant beam reaches up to the center of the roof to provide support.

It's one of 70 columns the construction team has added around the building to support the roof, which weighs 22,000 tons. The old columns are suspended in the air by the temporary columns and will stay propped up in that manner until crews build back up during 2020.

When finished, more than 600,000 cubic yards of dirt will have been removed, which will expand the arena's size from 400,000 square feet to 800,000.

Once the dirt has been removed and the crews have dug down, they'll begin building back up. That build-up includes reconnecting the suspended columns with new support structures to make the roof part of the new building.